July 18th Construction Update

The Contractor is anticipating concrete surfacing to be complete by the end of this week. Removals are scheduled for Tuesday of next week in Phase 6. The contractor will asphalt Monday prior to removals in Phase 6. The underground utility crew will begin installing sanitary sewer in the middle of next week once removals are complete.


Click here to review the updated Phasing Map.


If you have any questions regarding this project, please do not hesitate to reach out to Josh at (605) 759-6158.