July 9th Construction Update

We hope everyone had a fun and safe 4th of July weekend!


The contractor plans to have access to all driveways located within Phase 4 by Wednesday of next week. Concrete and Asphalt surfacing will continue throughout this week.


Removals in Phase 6 will begin once Phase 4 is complete, which is estimated to be next Tuesday.


Click here to review the updated Phasing Map.


If you have any questions regarding this project, please do not hesitate to reach out to Josh at (605) 759-6158.