June 17th Construction Update

Josh Thier

Throughout the past week, the contractor installed the underdrain and began installing base course in Phase 4. This week with the rain and unpredictable weather, the contractor hopes to begin concrete surfacing. Concrete surfacing is estimated to wrap up in the beginning of July. If you have any questions about driveways/approaches, please do not hesitate to call Josh at (605) 759-6158. The contractor is planning to have Phase 4 substantially complete by July 10th. When Phase 4 is substantially complete the contractor will begin removals in Phase 6.


Click here to review the updated phasing map.


If you have any questions regarding this project, please do not hesitate to call Josh at (605) 759-6158.


Contractor Paving 2nd Avenue between Academy Street and Garfield Street.

20 views0 comments

Recent Posts

See All

Comments


© 2023 Stockwell Engineers, Inc.

Stockwell Logo White.png

605-338-6668

Stockwell Engineers, Inc.

801 North Phillips Ave, Ste. 100

Sioux Falls, SD 57104

Founded Mark_f.png

605 338-4921

Asphalt Surfacing Company

1205 W. Russell Street

Sioux Falls, SD 57104

605 647-2286

City of Lennox

107 South Main Street

Lennox, SD 57039

Lennox - City - White - No Address.png
bottom of page