Despite the amount of rain we have received over the past week, the contractor continues to make progress on the project. Concrete surfacing will continue throughout the next week followed by asphalt. The contractor plans to have Phase 4 opened to traffic on the 10th of July. The contractor will begin removals in Phase 6 on July 10th once Phase 4 is open to traffic.
Click here to see the updated Phasing Map.
If you have any questions regarding this project, please do not hesitate to call Josh at (605) 759-6158.