June 6th Construction Update

The contractor will install the underdrain on Monday once all the dirt is cut down to the subgrade. The underdrain is estimated to take 3 days to install throughout Phase 4. Once the underdrain is installed, the contractor will install 12" of aggregate base course followed by concrete and asphalt surfacing. The contractor plans to have Phase 4 complete July 3rd. Phase 6 removals are estimated to take place July 8th.


Please click here to review the updated phasing map.


If you have any questions regarding this project, please do not hesitate to reach out to Josh at (605)-759-6158.


Contractor cutting down dirt to subgrade level on Elm Street.