top of page

November 2nd Construction Update

Josh Thier

Winter is around the corner and the contractor is pushing to finish Phases 2, 3, and 5. Throughout the past week, concrete in Phase 3 has been in full swing as the concrete was set in place including the sidewalks, approaches, and driveways. The contractor is estimating the concrete to be in place throughout Phase 2 and 3 by the middle of next week. Once all of the concrete is in place, the contractor will add topsoil throughout the two phases. Phase 3 will be opened up to thru traffic once topsoil is added which is estimated to be complete early next week.


The concrete crew slipped the curb and gutter throughout Phase 5 on Wednesday November 1st. The concrete crew will continue to work in Phase 2, 3, and 5 throughout the upcoming weeks. Once fillets and valley gutters are in place in Phase 5, the contractor is going to asphalt throughout the entire phase which is estimated to be complete November 10th. Driveways, approaches, and sidewalk will be followed by the asphalt.


Mailboxes in Phase 2 will be getting reset early next week.


If you have any questions or concerns regarding this project please do not hesitate to contact Josh at (605)-759-6158.




Curb and Gutter on Cedar Street in Phase 5


 
 
 

Comentarios


© 2023 Stockwell Engineers, Inc.

Stockwell Logo White.png

605-338-6668

Stockwell Engineers, Inc.

801 North Phillips Ave, Ste. 100

Sioux Falls, SD 57104

Founded Mark_f.png

605 338-4921

Asphalt Surfacing Company

1205 W. Russell Street

Sioux Falls, SD 57104

605 647-2286

City of Lennox

107 South Main Street

Lennox, SD 57039

Lennox - City - White - No Address.png
bottom of page