The weather conditions have caused a minor delay to the project however the contractor is working on the project again! The boring crew arrived on site Tuesday as they plan to bore the storm sewer underneath the railroad. The boring crew plans to be done by April 30th. The utility crew will be hooking up temporary water services today and tomorrow throughout phase 4. Once all of the water services are on the temporary watermain, the contractor will begin installing the sanitary sewer.
The contractor is estimating that Phase 4 will be completed in the middle of June. Once Phase 4 is complete the contractor will move into Phase 6.
If you have any questions or concerns regarding this project, please do not hesitate to reach out to Josh at (605) 759-6158.